The Bridge Boys' Home, Jimbolia, Timis County, Romania

Walls on the Up and Up

Date: Saturday 11 October 2003

Work is going steadily, we did not get much done this week due to rain. We are able to put up about 80 blocks a day, but I think that number will go up the closer we get to the pile of bricks and we start using more of the smaller ones. We have 2/3 of the first room up. We made it about 30cm larger than it was originally going to be.

Steve.